Întrebare:

Is it possible to reduce the work schedule from 5 days to 4 days a week, with a corresponding reduction in salary?

Răspuns:

Yes, in the case of temporary reduction of activity, for economic, technological, structural or similar reasons, for periods exceeding 30 working days, the employer may decide this, until the situation that caused the reduction of the program is remedied, after prior consultation with the representative union at the unit level or the employees' representatives, as the case may be.